Special Public Works Committee

Minutes Agenda City Website ↗

The Public Works Committee toured the aging city shop and reviewed roughly $469,000 in estimated repairs, including roof work and fire-safety door problems. No repair plan or spending decision was recorded at the special meeting.

The committee reviewed an estimated $468,950 in facility repairs, led by $327,000 for roof replacement. The shop has aging sections dating to before 1933, and staff reported a south-barn roof failure, failed heating equipment and door problems identified in a fire inspection.

Staff identified possible ways to reduce costs, including keeping the existing overhead doors while replacing openers, adding safety equipment and weather stripping, and having city crews complete some work. The record says further discussion was planned for the regular Public Works Committee meeting later that evening.

No public comments or communications recorded for this meeting.

PUBLIC WORKS FACILITY TOUR — DISCUSS PROPOSED REPAIRS AT PUBLIC WORKS FACILITY
At this special meeting, the committee toured the Public Works facility and reviewed proposed repairs. Staff reported that parts of the building date to before 1933; a section of the south-barn roof blew off in winter 2022-23, and a fire inspection found some service doors or hardware were difficult to use. The preliminary estimate totaled $468,950: $327,000 for roofs and $141,950 for other repairs. Staff also reported a failed garage exhaust scrubber/air handler expected to cost about $25,000 to replace, plus other air-handler needs not included in the original estimate; further discussion was planned for the regular committee meeting later that evening.