Two Rivers’ Community Development Authority gave a Sandy Bay Highlands lot owner a firm choice: meet the existing October construction deadline or return the lot by July 7 for the original $48,000 price, with a $10,000 penalty waived.

After a closed-session discussion of Sandy Bay Highlands purchase agreements, the CDA said it would not extend Mark Liska’s October 1, 2025 home-completion deadline. It offered to waive a $10,000 penalty if he agrees by July 7 to sell the lot back to the CDA for $48,000. The action sets a clear enforcement line for an undeveloped subdivision lot.

The CDA entered closed session by a 6-0 roll-call vote to discuss purchase agreements for undeveloped Sandy Bay Highlands parcels. The public record identifies the legal basis and topic, but not the private bargaining discussion.

Phase 3 infrastructure at Sandy Bay Highlands was reported as nearing completion, with electric and fiber expected by mid-July, gas by late August, and curb, gutter and base asphalt work planned for fall. The city also reported that two of four lots under contract with Lakeshore Residential were expected to close within two weeks.

No public comments or communications recorded for this meeting.

ELECTION OF OFFICERS FOR TERMS ENDING MAY 1, 2026 BIDC: Chair, Vice Chair, Secretary/Treasurer CDA: Chair, Vice Chair, Secretary/Treasurer
Passed
Both bodies retained the same officer slate through May 1, 2026. Gregory Coenen remains president/chair, Keith Lyons remains vice president/vice chair, and City Manager Gregory Buckley remains secretary-treasurer for both the BIDC and CDA. No other nominations were offered.
UPDATE ON SANDY BAY HIGHLANDS PHASE 3 CONSTRUCTION AND MARKETING
City Manager Gregory Buckley reported that the initial Phase 3 infrastructure contract, covering roadway gravel and water, sewer and storm sewer work, was nearing completion. Electric and fiber conduit work was underway and expected to finish by mid-July; natural-gas work was expected by the end of August. The city planned to seek bids in July for curb, gutter and base asphalt, with an August contract award and fall construction target. The city had signed listing agreements with Wiechert/Cornerstone, installed lot signage, and expected two of four Lakeshore Residential lot sales to close within two weeks.
UPDATE ON LOCAL DEVELOPMENT PROJECTS
Buckley provided updates on the Violet Inn, Pop Start Pizza and Darkside Strength projects. The minutes do not provide further details, commitments or decisions on those projects.
CLOSED EXECUTIVE SESSION OF THE CDA The Community Development Authority reserves the right to enter into closed session per Wis — Stats. 19.85(1)(e) deliberating or negotiating the purchasing of public properties, the investing of public funds, or conducting other specified public business, whenever competitive or bargaining reasons require a closed session --Consider status of purchase agreements with parcel owners in the Sandy Bay Highlands Subdivision
Passed
The CDA entered closed session at 5:40 p.m. to discuss the status of purchase agreements with owners of undeveloped Sandy Bay Highlands parcels. It cited the state-law exception for property purchases, public-fund investments or other public business where competitive or bargaining reasons require privacy. All six CDA members present voted yes; no members voted no.
RECONVENE IN OPEN SESSION Possible action on matters discussed in Closed Session
Passed
Following the closed session, the CDA directed staff to tell lot owner Mark Liska that it would not consider any further extension beyond October 1, 2025 for completing a home on his Sandy Bay Highlands lot. The October deadline had already been extended under a 2024 agreement. The CDA offered to waive the agreement’s $10,000 penalty if Liska signs by July 7 to return the lot to the CDA for the $48,000 he originally paid.