park facility improvements
Park upgrades, repairs, access, amenities, and maintenance planning.
What to Watch
Watch for construction updates confirming the Pierce Street reopening date, final Neshotah Park costs and grant amounts, and completion reports for earlier park projects.
Coming Up
Typically discussed at Advisory Recreation Board. Check back when the next agenda is published.
The Story
More than $700,000 in 2025 Neshotah Park improvements included Pierce Street resurfacing and parking work, with about half of the reported cost covered by grants. City Council heard June 2 that an archaeological review had briefly delayed the project; staff expected the stretch from 21st Street to Zlatnik Drive to close beginning June 3 and reopen before the July 4 weekend. Earlier parks updates also included proposed Paddlers Park shoreline and kayak-launch work, maintenance-tracking software, and a rock wall update, but later completion or approval details are not documented.
Record
-
Staff reported planned shoreline work at Paddlers Park, including native tall grasses intended to discourage geese and a paved kayak launch. Staff said an LNRP grant was expected to help cover costs, and the Environmental Advisory Board and Rotary had offered assistance.
Advisory Recreation Board -
Staff reported planned fall work at Zander Park, a hoped-for late-September launch of an updated golf simulator, and Picnic Hill disc-golf improvements dependent on volunteers.
Advisory Recreation Board -
Parks and Recreation reported it was adopting Productive Parks work-order software before the summer season. Staff said maintenance tasks had previously been tracked through supervisor knowledge, spreadsheets and whiteboards rather than a formal work-order system.
Advisory Recreation Board -
The agenda included a Parks and Recreation update on a rock wall installation; no discussion, vote, location, cost, funding source, or installation decision is documented.
City Council -
City Council discussed a brief delay to the Neshotah Park Pierce Street resurfacing and parking project while the State Historical Society reviewed an archaeological study.
City Council -
Staff said Pierce Street from 21st Street to Zlatnik Drive was expected to close for two to three weeks beginning June 3, with reopening planned before the July 4 weekend.
City Council -
The city reported more than $700,000 in Neshotah Park improvements for 2025, with about half funded by grants.
City Council