Active New

city hall parking deck repairs

Repairs and upkeep needed for the aging underground City Hall parking deck

Watch for an engineering inspection/report, a defined repair plan and timeline, and a funding discussion (budget vs. borrowing).

Typically discussed at City Council Work Session. Check back when the next agenda is published.

Council members and staff walked through the City Hall underground parking deck and were told repairs are likely within the next two to three years. There’s no public price tag or plan attached yet, but this is the kind of building fix that can turn into a big capital project once an engineer gets involved.

  1. Staff led a tour of the City Hall underground parking deck and highlighted infrastructure issues they said will need to be addressed within the next two or three years.

    City Council Work Session
  2. The item was handled as a discussion with no recorded vote, decision, or public hearing.

    City Council Work Session