Two Rivers’ Public Works Committee approved a $63,000 first-year upgrade to its asset-management software, with one dissent. It also mapped out a growing list of street, bridge and aging-facility needs without committing to most of them.
No public comments or communications recorded for this meeting.
Staff reported receiving notice to fill wetlands and said permitting plans were expected around May 10. The city planned to seek a permit covering the full parcel for flexibility, with final development decisions tied to lot demand and costs. Staff said biofilters would be used to treat runoff before it enters wetlands.
Staff said Roosevelt Avenue reconstruction had completed part of the sanitary sewer work and moved to water-main work. Storm-sewer work was planned at the 12th Street intersection, and public works staff expected to pave driving lanes there within weeks to accommodate traffic. Frontier telephone-line relocation was still scheduled, while Neshotah Park sidewalk work was reported below budget.
Public works staff continued concrete sidewalk work in Neshotah Park, including planned work along Pierce Street and 21st Street. The path was being slightly realigned to avoid a fiber-optic pedestal serving the concession stand and nearby area. Staff reported the current work was coming in below budget.
Staff reported replacing sidewalk around the Community House. They also identified sunken colored sidewalk near the Central Park flagpole by Washington Street and planned new sidewalk on the west side near the concession stand.
Staff identified sunken sidewalk on Washington Street downtown. Whether repairs can proceed will depend on a cost review and whether money is available.
Staff said the Wisconsin Department of Transportation would install a Columbus Street crosswalk as part of the Highway 42 resurfacing project if the city extends sidewalk along Columbus Street to Highway 42. The sidewalk extension is therefore the condition for adding the crosswalk.
The 19th Street project remained on hold while the city waits for more information about the confluence project. No action was recorded.
The East River Street project also remained on hold pending more information about the confluence project. No action was recorded.
Plans called for widening the bridge sidewalk by three feet rather than two and adding a parapet barrier wall. Staff was asking the state transportation department whether city public works staff could do the work. Earlier state sight-distance requirements had reduced the allowable parapet-wall design.
Staff said several tree grates south of 15th Street may need work. The minutes did not identify a repair schedule or funding decision.
The state requires an inventory of culverts between 6 and 20 feet. The city planned to do the work but was waiting for required information from the Wisconsin Department of Transportation.
A 2023 sewer-camera inspection found no evident problem in the sanitary main beneath the dip on 19th Street. The area is part of the 2024-25 lead-service-line work area, and staff said that work may reveal an issue that can be addressed then.
Staff reported receiving three speeding complaints on Lincoln Street in the prior week. The Police Department was asked to place a portable speed sign there in hopes of addressing the concern.
Staff identified Harbor Street from Pilon Street to 16th Street, 16th Street from Jackson Street to Emmet Street, and Emmet Street from 16th to 17th streets as proposed major 2025 projects. The Emmet Street work would connect the 12-inch water-river crossing to 17th Street.
Staff said its long-term plan is to reconstruct about one-quarter mile of streets and resurface about one-half mile annually, at an estimated $3.5 million per year. The future-needs list included street and bridge work, sewer inspections and equipment, traffic-signal upgrades, parking-lot resurfacing, and repairs at the public works shop. The shop needs included a roof estimated at $400,000 to $500,000, deteriorated structural elements, inoperable doors and a possible facility-needs study estimated at $50,000 to $100,000.
The committee approved upgrading the FASTER asset-management program to web-based utilities because the current version would no longer be supported after 2024. Staff estimated a first-year cost of $63,000 after discounts, including a one-time license fee, setup, data migration and training; annual support was listed at $15,750. Scott Stechmesser made the motion, Doug Brandt seconded it, and Bill LeClair dissented.
Roll call vote
0 yes
1 no