Joint Review Board

Minutes Agenda City Website ↗

The Joint Review Board unanimously approved expanding TID No. 12 and its project plan, allowing the city to pursue tax-increment financing support for two proposed investments.

The board unanimously approved Amendment No. 2 to TID No. 12. The amendment adds 0.988 acres and allows the city to pursue pay-as-you-go development grants of $150,000 and $130,000 for two investors, while listing possible future downtown street, pedestrian-safety and building projects if the district can afford them.

No public comments or communications recorded for this meeting.

REVIEW AND DISCUSSION OF PROPOSED AMENDMENT N — 2 TO THE PROJECT PLAN AND BOUNDARIES FOR TID NO. 12
Community Development Director/Planner Elizabeth Runge said TID No. 12 was created in 2018 to address blight and help build a new downtown hotel. She said two investors had approached the city for assistance, and the proposed amendment would add 0.988 acres to the district for one of those investments. Runge said the added area met the required minimum blight standard and that the city planned to develop pay-as-you-go grant agreements of $150,000 and $130,000 for the two projects. The plan also identified possible future spending on intersections, pedestrian safety at Washington and Lake streets, property acquisition, business assistance and the High Lift building, if financially feasible.
CONSIDERATION OF A RESOLUTION TO ADOPT AMENDMENT N — 2 TO THE PROJECT PLAN AND BOUNDARIES FOR TID NO. 12
Passed
The board approved the resolution adopting Amendment No. 2 to the TID No. 12 project plan and boundaries. The vote was unanimous by voice vote, but the minutes do not provide a numerical tally. The action authorizes the amended district plan described in the preceding discussion, including the boundary expansion and proposed financing framework.