Public Works Committee

Minutes Agenda City Website ↗

The Public Works Committee recommended ending east-side parking for one block of Jefferson Street after years of complaints about large vehicles narrowing the road. It also warned that a delayed state review could push Washington Street Bridge pedestrian work out of the 2024 construction season.

The committee recommended that City Council eliminate parking on the east side of Jefferson Street from 22nd to 23rd streets. Staff cited recurring congestion from large vehicles and trailers, including problems for buses and emergency-sized vehicles; the recommendation is narrower than police staff’s suggested restriction through 25th Street.

City staff said the Washington Street Bridge pedestrian project was still awaiting state review. Without a prompt response, the chance to bid, award and begin work during the 2024 construction season was fading.

Sandy Bay Highlands Phase 3 was out for bids, with an award recommendation expected to go to City Council July 15. Construction was not expected to start until after the Sept. 12-14 Parade of Homes.

No public comments or communications recorded for this meeting.

ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Sandy Bay Highlands Phase 3 update
The first portion of Sandy Bay Highlands Phase 3 was put out for bids, with bid opening scheduled for July 10. The base work covers part of Orchard Lane, its cul-de-sac and Rawley Court, while an add-on bid covers the rest of Orchard Lane and about 400 feet of Sandy Ridge Drive, including stormwater work. Staff expected to send an award recommendation to City Council on July 15, but construction was not expected to begin until after the Sept. 12-14 Parade of Homes.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Roosevelt Avenue reconstruction update
Staff reported that the sanitary sewer main was complete. Crews were finishing the water main, water services and sanitary laterals, with water-main completion expected the week of July 8 before work moved to the main storm sewer.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Washington Street Bridge - pedestrian accommodations
Plans for pedestrian accommodations at the Washington Street Bridge were submitted to the Wisconsin Department of Transportation on May 28, but staff had not received a response by July 3. Staff said the window to bid, award and start construction in 2024 was fading. The city also asked whether its own crews could do the work, which staff said could make a 2024 completion more feasible.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — FASTER migration
Staff said the migration to the FASTER system was moving ahead and that the city had access to its online version. The vendor shortened its estimated migration and training timeline from 16 weeks to six to eight weeks.
DISCUSSIONS OR ISSUES ON HOLD, PENDING FURTHER INVESTIGATION — WDOT small bridge/culvert inventory
Staff had no update on state inventory requirements for small bridges and culverts. The city had identified six possible locations that may need inspection, depending on how the state classifies the requirements.
COMMITTEE AND COUNCIL MEMBER ITEMS FOR DISCUSSION, INCLUSION IN FUTURE AGENDA AND ACTION, IF NEEDED — STH 310 - WDOT Project - July 8 - November, 2024
State Highway 310 construction was scheduled to begin the week of July 8 and finish in October. Staff said most work should be done before Labor Day, followed by a planned 12-day closure of the roundabouts at County Highways R, Q and B.
DISCUSS STAFF RECOMMENDATIONS (TRAFFIC AND PARKING CONTROL) - ACTION, ENDORSEMENT OR MODIFICATIONS, AS NEEDED — Citizen traffic signage concerns - various locations
A resident raised concerns about sign sizes, warning signs, parking and route signs at several locations. Staff said the signs generally met state traffic-control standards and that unnecessary warning signs can reduce respect for signs. Committee members Scott Stechmesser and Doug Brandt agreed to leave the existing signs at Lincoln Avenue and 22nd Street unchanged; staff recorded no action on the other requests.
DISCUSS STAFF RECOMMENDATIONS (TRAFFIC AND PARKING CONTROL) - ACTION, ENDORSEMENT OR MODIFICATIONS, AS NEEDED — Discussion of on street parking on Jefferson Street north of 22nd Street
Passed
The committee revisited a long-running concern about vehicles and trailers parked on both sides of Jefferson Street north of 22nd Street. Staff said the conditions can make the street difficult for buses, fire trucks and other large vehicles to pass, though police said much of the parking was within current rules. The committee recommended that City Council eliminate east-side parking from 22nd to 23rd streets, and directed public works staff to notify residents before the council meeting.
OTHER ITEMS THAT MAY COME BEFORE THE COMMITTEE: CONSIDERATION AND ACTION, IF NEEDED
The committee raised a question about how much of a sidewalk must remain clear of bushes, grass, snow, fences and other encroachments. Staff also reported that its concrete supplier’s plant outage had delayed work, including open ditches awaiting concrete, and said the department would seek another supplier in the short term. Public works crews also secured an entrance and lower window at the former St. Mark’s School after the owner did not respond to reports of a broken glass door.