street paving

Resurfacing and repairing neighborhood streets, curbs, and gutters.

Watch for the bid package release and any later contract award that sets a real schedule for Emmet, 18th, and 19th Streets.

Typically discussed at Public Works Committee. Check back when the next agenda is published.

Emmet, 18th, and 19th Streets keep coming up as 2026 resurfacing targets, but staff says utility contracts are ahead of the paving work. That likely affects when those blocks see crews, cones, and smoother pavement.

  1. passed 8-0 City Council · Sep 2, 2025

    25-175 Award of bid for contract 6-2025: Curb & Gutter and Paving (Sandy Bay Highlands Subdivision No. 3)

    Motion to award the contract to Vinton Construction Company of Manitowoc, based on its lowest qualified bid, in the amount of $342,593.90

    Shannon Derby Yes
    Bill LeClair Yes
    Doug Brandt Yes
    Tim Petri Yes
    Scott Stechmesser Yes
    Adam Wachowski Yes
    Darla LeClair Yes
    Mark Bittner Yes
  1. A Public Utilities Committee agenda included a tracked appearance of the topic street paving.

    Public Utilities Committee
  2. A City Council agenda included an item titled "CONSTRUCTION PROJECTS" associated with street paving.

    City Council
  3. A city agenda status update item included “Neshotah Park - Pierce Street Resurfacing and Parking Improvements.”

    Public Utilities Committee
  4. City Council discussed the draft FY2026 budget, including a proposed 3.8% levy increase and use of one-time items (including land sales, a debt premium, and a cell-tower payment) to balance the year.

    City Council
  5. City Council discussion of the draft FY2026 budget included unresolved choices affecting services (cemetery flower funding, library funding level requested by the Library Board, and special events funding structure).

    City Council
  6. City Council awarded Contract 6-2025 (curb, gutter, and paving for Sandy Bay Highlands Subdivision No. 3) to Vinton Construction Company of Manitowoc for $342,593.90 as the lowest qualified bid.

    City Council
  7. The Sandy Bay Highlands Subdivision No. 3 paving-related contract award passed 8-0; minutes note Councilmember Bonnie Shimulunas arrived during the voting.

    City Council
  8. DPW said it intends to bid mill-and-pave work for Emmet, 18th, and 19th Streets early in 2026, with construction starting soon after remaining east-side lead service lateral work is finished.

    City Council Work Session
  9. DPW indicated the resurfacing schedule is being sequenced to avoid paving streets and then reopening them for utility work.

    City Council Work Session
  10. An agenda included an item titled “Lake Street (McDonalds/Seagull Marina/DPW Campus) and Memorial Drive Concern Update.”

    City Council Work Session
  11. Staff reported plans, specifications, and bid documents for 2026 resurfacing on Emmet, 18th, and 19th Streets were being prepared and should be ready soon; no schedule or cost details were included in the minutes.

    Public Works Committee
  12. Staff reported they are preparing plans and bid documents for Emmet, 18th, and 19th Streets, and said utility contracts are taking priority over the resurfacing work.

    Public Works Committee
  13. Staff said plans and bid documents are being prepared for Emmet, 18th, and 19th Streets, and utility contracts are taking priority over the resurfacing work at that time.

    Public Works Committee