east river trail improvements

Improvements to the East River Trail and nearby parking lot.

Watch for confirmation that the easement was recorded and for a revised construction timeline.

Typically discussed at Public Works Committee. Check back when the next agenda is published.

The East River Trail and parking lot project fell behind its hoped-for completion before the car cruise and show. Staff said the needed easement was signed and expected to be recorded, but storm recovery work delayed the project and the city must set a new schedule.

  1. Staff reported that the easement for the East River Trail and parking lot project had been signed and was expected to be recorded that week.

    Public Works Committee
  2. Staff said storm recovery work delayed the project schedule, which had been aimed at completion before the car cruise and show.

    Public Works Committee
  3. Staff said the city needs to reset the project timeline.

    Public Works Committee