Council voted 8-0 to preserve state-loan reimbursement for a 2027 project targeting 500 service connections and 11,600 feet of 90- to 100-year-old sewer main. The vote does not approve construction or finalize borrowing, which could reach $11.5 million.

  1. passed 8-0 City Council Work Session · Jun 29, 2026

    Resolution Declaring Intent to Reimburse Expenditures from Proceeds of Borrowing for 2027 Sewer Rehabilitation and Water-Sewer Lateral Replacement Projects

    Motion to approve the Resolution Declaring Intent to Reimburse Expenditures from Proceeds of Borrowing for 2027 Sewer Rehabilitation and Water-Sewer Lateral Replacement Projects

  1. Council approved, 8-0, a resolution allowing the city to pay eligible early costs for planned 2027 sewer rehabilitation and water-sewer lateral replacement work, then reimburse itself with state Clean Water and Safe Drinking Water Fund financing.

    City Council Work Session
  2. The planned 2027 work includes about 11,600 feet of sanitary sewer main, described as 90 to 100 years old, and 500 individual service connections, including an effort to replace lead service laterals while federal infrastructure funding remains available.

    City Council Work Session
  3. The reimbursement resolution was required by the Wisconsin Department of Natural Resources before June 30, 2026, to preserve eligibility for reimbursement of early project costs. It does not approve construction or set final borrowing; anticipated borrowing is not to exceed $11.5 million.