Two Rivers adopted a new Main Street and waterfront overlay district, but stripped out proposed design standards and the ban on stand-alone parking lots. The council also approved a contested Jefferson Street parking restriction and delayed a $1 million subdivision infrastructure bid.
Council approved the tattoo-parlor conditional-use permit unanimously. It added requirements that the business maintain a valid state or county establishment permit and that every tattoo or piercing practitioner hold a valid state license. Two residents questioned the operator's reported history and how the city would verify licensing; the council's added conditions make valid licensing an explicit condition of the local permit.
Public Input: Andre Robitalille questioned whether the operator had been operating illegally in Milwaukee and how permit compliance would be checked. Susan Robitalille raised concerns about underage tattooing and asked the city to ensure licenses and permits remain current; no one spoke during the second or third calls.
Council adopted the Main Street and Waterfront Corridor Overlay District after rejecting one proposed amendment and then unanimously approving a different version. The adopted version removed the proposed ban on stand-alone parking lots and removed exterior design standards, while adding outdoor-storage provisions and directing the Plan Commission to consider expanding the district boundaries. The changes substantially narrowed the original proposal's controls over new development, even as the council retained the overlay district itself.
Public Input: Mark Gordon objected to the proposed ban on parking lots as a principal use. Bill Kiel said the waterfront boundary left out significant waterfront areas and asked the council to table the item; Andre Robitalille said city zoning has major gaps compared with the comprehensive plan; Amy Polkhoff raised concerns about outdoor storage; and the city received a written objection from Circle B Bison Ranch, LLC. Jason Ring said Main Street supported the overlay district but wanted parking addressed and outdoor storage substituted.
Council approved eliminating parking on the east side of Jefferson Street from 22nd to 23rd streets. The vote was divided: five members supported it, three opposed it and Tim Petri abstained. Residents had questioned the timing of notice and raised concerns about speeding and large-vehicle access, but the minutes do not record council members' reasons for their votes.
Council tabled the proposed award to Advance Construction of Green Bay and will revisit it at the July 29 work session. The project was budgeted at $1 million, and staff was still deciding whether to recommend the base bid or a larger alternate scope. The delay means the council did not award the construction contract at this meeting.
Council unanimously adopted an amended resolution setting conditions for a possible referendum question on exceeding the city's levy limit to help fund community-pool operations. The minutes do not spell out the resolution's conditions or confirm that a referendum was placed on a ballot. The action keeps a potential tax-limit referendum in play rather than approving pool operations funding itself.
City Manager Greg Buckley said city staff had an upcoming meeting with Manitowoc County representatives about using county ARPA matching funds in recently approved contracts for lead water-service lateral replacement. No council action was taken. Residents should watch whether the county funds are committed and how they are allocated among the contracts.
The developer did not sign the three-month extension agreement for The Confluence Project by the July 31 deadline, according to the city manager. The extension had required a $30,000 nonrefundable fee; the developer said it remained interested in the site but was conducting a market study and cited high interest rates for the delay. The city did not take action at this meeting, leaving the future of the city-owned former Eggers downtown site unresolved.
The city manager said the developer was still working toward project financing and a site purchase by the end of August. He expected to bring back a modified development agreement, and the developer was seeking an additional $200,000 in city tax-increment financing assistance beyond the $500,000 in the original agreement. No additional assistance was approved at this meeting.