Two Rivers utilities staff reported a looming lead-service inventory deadline, a transformer outage expected to last months, and several 2025 infrastructure needs that will require borrowing or further budget decisions. The committee took no substantive recorded votes.
Key Decisions
The Water Utility faced an Oct. 16 deadline to submit its inventory of known lead, galvanized and unknown water services. After filing, it had 30 days to notify affected property owners about their service type and replacement options.
A worn transformer component at the Columbus Substation was expected to cost about $15,870 and had a 42-week lead time, leaving Unit 1 offline until repairs are complete. Staff also reported early signs that future power-contract costs could rise, potentially becoming a bigger issue in 2027.
Staff said three wastewater-facility roofs need replacement and proposed borrowing for the work as a 2025 capital project after a failed pump motor displaced the planned 2024 roof spending. The committee also heard that substantial sewer-pipe lining work is proposed for 2025.
Public Input
No public comments or communications recorded for this meeting.
Agenda Items
CONSTRUCTION PROJECTS — Roosevelt Avenue Reconstruction update
Staff reported that the last concrete pavement work was expected that week, followed by topsoil, sod, signs and pavement markings. The project was expected to finish within one to two weeks.
CONSTRUCTION PROJECTS — 2024 Scattered LSL Project update
The contractor began work near 34th Street in late September, replacing lead water services and faulty sanitary laterals. Pavement restoration was to follow as work continued.
CONSTRUCTION PROJECTS — Sandy Bay Highlands Phase 3 Project update
The subdivision plat had been sent to the state for review in mid-September, a process staff said usually takes about 30 days. A preconstruction meeting was set for Oct. 14, with construction planned to begin Oct. 21 and the initial work expected around Thanksgiving.
Staff described the 2025 Harbor, Emmet and 16th streets project as primarily a reconstruction project. A central goal is connecting the 12-inch water main river crossing to the 12-inch main at 17th Street.
Staff reported that three wastewater-facility roofs need replacement. Money reserved in the 2024 budget for one roof was redirected after a pump motor failed, and staff said the utility would borrow funds to complete the roofs as a 2025 capital project.
WASTEWATER UTILITY: UPDATES AND ACTION — Sludge Hauling - update
Sludge hauling was expected to begin in the middle of the week. Staff said higher-strength incoming wastewater was producing more sludge that must be disposed of through land application.
WASTEWATER UTILITY: UPDATES AND ACTION — Sludge Press Final Inspection
The Wisconsin Department of Natural Resources completed its final walkthrough of the new sludge screw press. The inspection allows the utility's state loan contract to be closed out.
WASTEWATER UTILITY: UPDATES AND ACTION — Clarifier Final Repair Work
Staff said deteriorating rings on the primary clarifiers had been found below the water line in 2023. After repairs to one clarifier last fall, work on the second clarifier ring was being completed that week.
WASTEWATER UTILITY: UPDATES AND ACTION — Sludge Management Program update E.
The utility submitted an updated sludge-management plan required under its new state permit, but the Department of Natural Resources returned it with additional comments and requests. Staff said they were revising the plan and intended to resubmit it soon.
CMOM Time Extension ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE 1 — Columbus Substation Unit 1 Transformer Bushing Replacement
The utility received an extension from the Department of Natural Resources until Jan. 31, 2025, to update and submit its CMOM wastewater-management plan after missing the original Oct. 31 deadline. Separately, an inspection found worn bushings on Columbus Substation Unit 1; replacement was estimated at about $15,870 with a 42-week lead time, and the transformer would remain offline until repaired.
CMOM Time Extension ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE 1 — 2025 Bucket Truck update
Delivery of the utility's new bucket truck was pushed from April 2025 to October 2025. Staff said they would explore financing it through a WPPI 10-year, zero-interest loan with a 1% down payment.
CMOM Time Extension ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE 1 — WPPI Conference Recap
Staff reported that preliminary responses to WPPI's search for next-generation power-production contracts pointed to higher rates, though they said this was not an immediate concern and could become a larger factor in 2027. The committee also heard that some community members had been approached about data centers, including one that could require about 600 megawatts of system demand and related upgrades, and that there was interest in small solar projects on publicly owned brownfields.
WATER UTILITY: DIRECTOR UPDATE, DISCUSSION AND ACTION, AS NEEDED — LCRR Deadline and Progress
The Water Utility was working toward an Oct. 16 deadline to submit a centralized inventory of all known lead, galvanized and unknown water services in the city. After submitting the inventory, the utility had 30 days to notify affected properties about their service type and possible replacement options. Staff also noted that federal funding questions remained unresolved for the broader national effort to remove lead services over the next decade.
WATER UTILITY: DIRECTOR UPDATE, DISCUSSION AND ACTION, AS NEEDED — 2025 Budget
Staff said there was little new budget information to report. A joint Personnel and Finance Committee/Public Utilities Committee meeting was scheduled for Oct. 30 to review the 2025 utility budgets.
WATER UTILITY: DIRECTOR UPDATE, DISCUSSION AND ACTION, AS NEEDED — South Tower Driveway
A survey found that part of the South Water Tower driveway is on private property. Staff said they were taking steps with the property owner to resolve the encroachment and install a privacy and security fence.
WATER UTILITY: DIRECTOR UPDATE, DISCUSSION AND ACTION, AS NEEDED — 2025 East Tower Repairs
The Water Utility canceled its existing inspection contract, which staff said gives it more control over the timing and scope of repairs. The East Tower was to be drained for an inspection of reportedly failed roof-to-wall connections and development of a repair proposal for spring 2025. Staff said the South Tower also needs interior work, but likely on a three- to five-year timeline because spot repairs were recently completed.
STORM WATER UTILITY: UPDATES AND ACTION, AS NEEDED — 2024 Leaf Pick Up
Leaf pickup was expected to begin around Oct. 14 and continue into early December, depending on weather. Public Works planned to use multiple collection zones again and post progress updates on the city website and Facebook page.
SOLID WASTE UTILITY: UPDATES AND ACTION, AS NEEDED — Landfill update
The city still needed to complete an effluent-collection system to control landfill seepage. Public Works had received a contractor quote and needed to determine whether the work required public bidding or could proceed using the quote.