Two Rivers utilities staff flagged a possible 2026 solid-waste fee increase and began planning a pressure-relief fix after water-main breaks in the city’s north side.
Key Decisions
Residents could face higher solid-waste fees in 2026 because the city’s collection agreement has steep cost increases in its first three years. The committee discussed possible changes to garbage stickers, the environmental fee or how that fee is allocated, but made no decision.
Water staff said pressure surges in the north side’s system can contribute to water-main breaks because that area lacks a water tower to absorb excess pressure. They are collecting data and hope to engineer a pressure-relief system for possible installation in 2026.
Riverside Foods’ grease-trap cleaning briefly reduced solids reaching the wastewater plant, but high suspended-solids levels returned within about a week. Staff said the company may need weekly cleaning and had not arranged outside waste monitoring.
Public Input
No public comments or communications recorded for this meeting.
Agenda Items
CONSTRUCTION PROJECTS — 2024-2025 Lead Service Lateral Project update
The city reported 53 public-side water-service replacements, three private-side replacements, 32 sanitary laterals within the right-of-way and one outside it. Pavement restoration was complete on 32nd, 33rd and 34th streets, but weather and frost were expected to halt further work for the year. Staff said possible work on 31st Street could resume the week of Dec. 9 if weather allowed.
CONSTRUCTION PROJECTS — Sandy Bay Highlands Phase 3 update
The first portion of Sandy Bay Highlands Phase 3 had sanitary sewer, water main and services, and storm-sewer laterals installed. Rain and the holiday weekend delayed grading and gravel work. The contractor hoped to finish grading and graveling that section by the end of the first week of December before returning to underground utility work.
WASTEWATER UTILITY: UPDATES AND ACTION — Riverside Foods update
Wastewater and engineering staff observed Riverside Foods’ grease-trap cleaning in mid-November and found floatable material, surface grease and substantial sludge. Solids reaching the wastewater plant dropped after cleaning, then rose again; suspended solids exceeded 1,000 on Nov. 25 and 26, compared with a typical level around 200. Staff said Riverside Foods may need weekly cleaning and had not arranged monitoring through a private testing lab.
ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE — Columbus Substation update
The Columbus Substation returned to two feed lines on Nov. 20 after ATC completed maintenance. Unit 1 remained offline, with repairs anticipated in spring 2025.
ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE — Tree Trimming
The Electric Utility notified east-side residents that tree trimming near power lines would begin soon. The work will target trees within 10 feet of primary lines and two feet of secondary lines.
ELECTRIC AND TELECOMMUNICATIONS UTILITIES: DIRECTOR UPDATES AND ACTION, IF APPLICABLE — Department Project update
The department was wrapping up year-end projects and working to energize the Braun development. After year-end paperwork, staff planned to begin tree trimming and inventory work.
Andrew Sukowaty reported several recent water breaks, including one on a private industrial water service that was suspected of leaking for more than a week before it surfaced. He said the north side lacks a water tower to absorb pressure surges, allowing pressure to bounce through the system and occasionally break mains. The Water Utility is collecting pressure data and hopes to engineer a pressure-relief system for possible implementation in 2026.
STORM WATER UTILITY: UPDATES AND ACTION, AS NEEDED
Staff reported work to update the city’s GIS drainage-basin and best-management-practice information, along with WinSLAMM stormwater-model inputs, under the Urban Nonpoint Stormwater Grant.
SOLID WASTE UTILITY: UPDATES AND ACTION, AS NEEDED
During 2025 budget work, staff identified the potential need for a 2026 solid-waste fee increase to cover a collection agreement that began in 2024 and has significant increases in its first three years. Possible options include changing garbage-collection stickers, changing the environmental fee or changing how that fee is allocated. The committee made no decision and said the issue would return for further discussion.
ANY OTHER ITEMS OR ISSUES TO COME BEFORE THE COMMITTEE, WITH DISCUSSION AND ACTION 1
Tim Petri raised resident confusion over utility-bill usage fees and minimum-usage charges. He said residents were asking for clearer explanations or different wording so the charges’ purpose and meaning are easier to understand.