Two Rivers’ public-works committee flagged a major mismatch between its written street-assessment policy and what homeowners have actually been charged since 2019. It also received updates on Memorial Drive work, delayed park improvements and aging traffic signals.

The committee was told the written policy calls for adjacent property owners to pay 75% of eligible reconstruction costs, but the city has been charging them about 30% since 2019 and absorbing nearly 70%. Staff will examine whether to keep the practice, rewrite the policy or consider a wheel tax instead of residential assessments.

Memorial Drive’s bridge was expected to remain closed until it needed to reopen, no later than May 23, while paving and other work continued. Staff expected the bridge, sidewalk and trail to be open for Memorial Day and the June 1 marathon, with through traffic returning on one lane after May 23.

The city is considering returning to the state funding queue for Washington Street traffic-signal upgrades after the earlier effort stalled over higher city costs. Staff reported recurring problems with flashing signals and pedestrian audio notices.

No public comments or communications recorded for this meeting.

ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Harbor Street, 16th Street and Emmet Street Reconstruction
Staff said contracts awarded the previous month were still being executed. Preliminary talks with Vinton Construction had occurred, but the project start was pushed to about mid- to late July because of the bidding and award timeline. Staff said the revised start should still leave enough time to complete the work.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Pierce Street Update
The Pierce Street project had been delayed while the city awaited historical and state grant approvals for work affecting proposed parking lots and trails. Staff said the Wisconsin Department of Natural Resources authorized the project to proceed late that day, and the city was checking contractor availability. Public Works crews could begin trail work as early as the week of May 12.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Public Works Shop Repairs Update
Staff reported progress on overhead-door equipment, column repairs and service doors at the Public Works shop. Roof work, because of its cost, will need to be formally bid and awarded before it can proceed.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Memorial Drive DOT Project Update
Staff reported that concrete pavement repairs had shifted to outside travel lanes and shoulders, while bridge-deck overlay work had been completed and was curing. The bridge was to remain closed until reopening was necessary, with May 23 identified as the required reopening date. Staff expected paving work to finish by May 23, allowing through traffic to use one lane while remaining work continued; the bridge and its sidewalk/trail were expected to be open for Memorial Day and the June 1 marathon.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — Colored Concrete Crosswalk - 15th & Washington
Public Works reported weather delays on the colored concrete crosswalk at 15th and Washington because rain can damage uncured colored concrete. Staff expected the work to be finished during the week of May 12.
ONGOING PROJECT STATUS AND ACTION, IF NEEDED — RRFB's
Staff said plans, updated material pricing from TAPCO and Wisconsin Department of Transportation approvals were still needed for pedestrian crossing beacons at Washington and 12th streets and Memorial Drive and Madison Street. The city was aiming to have those pieces in place for installation later in the summer or early fall.
DISCUSSIONS OR ISSUES ON HOLD, PENDING FURTHER INVESTIGATION — Snow Sidewalk Clearing - Hold
The sidewalk snow-clearing issue remained on hold. Staff said questions had been sent to city attorneys and the committee was waiting for a chance to discuss their responses.
DISCUSS STAFF RECOMMENDATIONS (TRAFFIC AND PARKING CONTROL) - ACTION, ENDORSEMENT OR MODIFICATIONS, AS NEEDED — Traffic Signal Updates Discussion 1
Staff said the city began pursuing upgrades to Washington Street traffic signals between 16th and 22nd streets in 2021-22, but stopped after a state maintenance-contract rebid would have significantly increased the city’s cost. The aging signals have reportedly stayed in flashing mode during damp mornings, and pedestrian audio notifications do not always work. Staff is exploring whether the city can reenter the state funding queue for upgrades.
OTHER ITEMS THAT MAY COME BEFORE THE COMMITTEE: CONSIDERATION AND ACTION, IF NEEDED — Assessment Policy Discussion
Staff told the committee that the written assessment policy assigns 75% of eligible project costs to adjacent properties and 25% to the city, but the city has instead charged adjacent owners about 30% since a 2019 committee discussion. That means the city has been absorbing nearly 70% of eligible costs without the written policy matching the practice. Staff said the committee will examine whether to retain the current practice, revise the policy to match it, adopt a different split or consider a wheel tax in place of residential assessments.
2026 Budget DPW has been looking at future budget needs that include traffic signals, assessment policy and staffing.
Staff said the 2026 budget discussion includes possible costs for traffic signals, assessment policy changes and staffing. The Wisconsin Department of Natural Resources said the city needs two certified sanitary-sewer collection-system operators, including one from Public Works, which could add costs. Staff also identified a possible need for another Public Works engineer and a GIS staff member while planning the capital program and five-year needs.