Two Rivers’ public-works committee flagged a major mismatch between its written street-assessment policy and what homeowners have actually been charged since 2019. It also received updates on Memorial Drive work, delayed park improvements and aging traffic signals.
No public comments or communications recorded for this meeting.
Staff said contracts awarded the previous month were still being executed. Preliminary talks with Vinton Construction had occurred, but the project start was pushed to about mid- to late July because of the bidding and award timeline. Staff said the revised start should still leave enough time to complete the work.
The Pierce Street project had been delayed while the city awaited historical and state grant approvals for work affecting proposed parking lots and trails. Staff said the Wisconsin Department of Natural Resources authorized the project to proceed late that day, and the city was checking contractor availability. Public Works crews could begin trail work as early as the week of May 12.
Staff reported progress on overhead-door equipment, column repairs and service doors at the Public Works shop. Roof work, because of its cost, will need to be formally bid and awarded before it can proceed.
Staff reported that concrete pavement repairs had shifted to outside travel lanes and shoulders, while bridge-deck overlay work had been completed and was curing. The bridge was to remain closed until reopening was necessary, with May 23 identified as the required reopening date. Staff expected paving work to finish by May 23, allowing through traffic to use one lane while remaining work continued; the bridge and its sidewalk/trail were expected to be open for Memorial Day and the June 1 marathon.
Public Works reported weather delays on the colored concrete crosswalk at 15th and Washington because rain can damage uncured colored concrete. Staff expected the work to be finished during the week of May 12.
Staff said plans, updated material pricing from TAPCO and Wisconsin Department of Transportation approvals were still needed for pedestrian crossing beacons at Washington and 12th streets and Memorial Drive and Madison Street. The city was aiming to have those pieces in place for installation later in the summer or early fall.
The sidewalk snow-clearing issue remained on hold. Staff said questions had been sent to city attorneys and the committee was waiting for a chance to discuss their responses.
Staff said the city began pursuing upgrades to Washington Street traffic signals between 16th and 22nd streets in 2021-22, but stopped after a state maintenance-contract rebid would have significantly increased the city’s cost. The aging signals have reportedly stayed in flashing mode during damp mornings, and pedestrian audio notifications do not always work. Staff is exploring whether the city can reenter the state funding queue for upgrades.
Staff told the committee that the written assessment policy assigns 75% of eligible project costs to adjacent properties and 25% to the city, but the city has instead charged adjacent owners about 30% since a 2019 committee discussion. That means the city has been absorbing nearly 70% of eligible costs without the written policy matching the practice. Staff said the committee will examine whether to retain the current practice, revise the policy to match it, adopt a different split or consider a wheel tax in place of residential assessments.
Staff said the 2026 budget discussion includes possible costs for traffic signals, assessment policy changes and staffing. The Wisconsin Department of Natural Resources said the city needs two certified sanitary-sewer collection-system operators, including one from Public Works, which could add costs. Staff also identified a possible need for another Public Works engineer and a GIS staff member while planning the capital program and five-year needs.