Water main work and land-use changes along Lincoln Avenue.

Construction timing, traffic control, and any planned water shutoffs for the STH 42/Lincoln Ave water main replacement.

Typically discussed at City Council. Check back when the next agenda is published.

Two separate Lincoln Ave items wrapped up at Council: a zoning change at 3204 Lincoln Ave (8-0, no one spoke at the hearing) and a contract to replace about 2,200 feet of water main on STH 42/Lincoln Ave (9-0). For residents nearby, the zoning vote affects what can be built/used on those lots, and the water main job affects traffic and water service planning during construction.

  1. passed 9-0 City Council · Apr 6, 2026

    26-056 Competitive Bid Award for Contract 1-2026 for Water Main Improvements on State Highway 42/Lincoln Avenue in the Base Bid Amount of $349,985, Plus a 10% Contingency, in the Total Amount Not-to-Exceed $384,983.50

    Motion to award the contract to Vinton Construction Company of Manitowoc, based on its lowest qualified bid, in the amount of $349,985.00 (26-056 Contract 1-2026 Water Main Improvements on State Highway 42/Lincoln Avenue)

    Mark Bittner Yes
    Darla LeClair Yes
    Adam Wachowski Yes
    Scott Stechmesser Yes
    Bonnie Shimulunas Yes
    Tim Petri Yes
    Bill LeClair Yes
    Doug Brandt Yes
    Shannon Derby Yes
  2. passed 8-0 City Council · Feb 2, 2026

    26-016 Public Hearing for a Request to Rezone, from IPF to R-3, Located at 3204 Lincoln Ave, and Parcel No. 053-162-301075.00 (newly created Lots 2 & 3), Submitted by Applicant and Owner Renew Church Inc.

    Motion to approve request per recommendation of the Plan Commission

    Doug Brandt Yes
    Shannon Derby Yes
    Bill LeClair Yes
    Darla LeClair Yes
    Tim Petri Yes
    Bonnie Shimulunas Yes
    Scott Stechmesser Yes
    Adam Wachowski Yes
  3. passed 7-0 Plan Commission · Jan 12, 2026

    Review request to rezone, from IPF to R-3, located at 3204 Lincoln Ave, and Parcel No. 053-162-301-075.00 (newly created Lots 2 & 3), submitted by applicant and owner Renew Church Inc.

    Motion made to recommend approval of the rezoning of Lots 2 & 3 on the CSM (3204 Lincoln Avenue & Parcel No. 053-162-301-075.00) to the City Council.

    Adam Wachowski Yes
    Pat Klein Yes
    Matt Heckenlaible Yes
    Kristin Lee Yes
    Kay Koach Yes
    Rick Inman Yes
    Kyle Kordell Yes
  1. Staff reported WDOT planned to grind off incorrect pavement markings on the Washington Street Bridge and re-mark the correct area; some discoloration could remain.

    Public Works Committee
  2. Staff reported shrinkage cracking was observed in the concrete bridge overlay, and WDOT indicated the deck will likely need epoxy sealing within the next several years.

    Public Works Committee
  3. Council held a public hearing on a zoning change request for 3204 Lincoln Ave (Renew Church Inc.), changing two newly created lots from IPF to Residential R-3 while keeping the larger lot as IPF.

    City Council
  4. The stated reason for the zoning change was to address a zoning nonconformity created when a housing dwelling and an institutional building were operating on the same lot after a lot subdivision.

    City Council
  5. No one spoke during the public hearing after three calls for public input.

    City Council
  6. Council approved the zoning change request by an 8-0 vote.

    City Council
  7. Council awarded Contract 1-2026 for water main improvements on STH 42/Lincoln Avenue to Vinton Construction Company for $349,985, with a 10% contingency for a total not-to-exceed of $384,983.50.

    City Council
  8. The contract scope described included replacement of approximately 2,200 feet of water main along STH 42/Lincoln Avenue.

    City Council
  9. Agenda materials stated the bid opening occurred March 26, 2026 and identified Vinton Construction Company as the lowest responsible bidder.

    City Council
  10. Council approved the contract award by a 9-0 vote.