Active

storm damage recovery

Storm damage cleanup, repairs, utility help, and disaster recovery funding

Illustration for storm damage recovery
AI image
Watch for a formal leaf-collection schedule change, final sidewalk repair costs, and revised timelines for crosswalk and City Hall parking-deck work.

Typically discussed at Public Utilities Committee. Check back when the next agenda is published.

The May 17 windstorm left the city weighing a 2–3 week shorter leaf-collection season while crews handle cleanup and repairs. Public Works counted more than 360 brush loads, estimated at least $20,000 in sidewalk-panel replacements, and expects delays to other planned work.

  1. passed Public Utilities Committee · Jun 1, 2026

    Out-of-State Mutual Aid Agreement - Action Item

    Motion to accept the Out-of-State Mutual Aid Agreement

  2. passed 9-0 City Council · Jan 19, 2026

    26-013 Resolution Authorizing Letter of Support for State Individual Assistance Program

    Motion made by Bittner, seconded by Derby to adopt the resolution.

  1. City Council unanimously passed Resolution 26-013 authorizing a letter supporting a proposed state disaster-recovery grant program for individuals and businesses when federal aid is unavailable.

    City Council
  2. The proposed state program would set aside $30 million for people and businesses affected by natural disasters, contingent on state legislation being enacted.

    City Council
  3. Electric utility staff reviewed the April 19 storm response, including mutual-aid crews from multiple cities and specialized equipment used to replace poles and restore service.

    Public Utilities Committee
  4. Wastewater staff reported that the May 17 windstorm caused outages at the treatment plant and 11 lift stations. Crews rotated portable generators and pumps for about 23 consecutive hours to prevent overflows.

    Public Utilities Committee
  5. The Public Utilities Committee accepted MEUW’s out-of-state mutual-aid agreement, setting billable rates for labor, equipment and other costs when utilities assist each other across state lines.

    Public Utilities Committee
  6. Public Works reported handling more than 360 loads of brush after the May 17 windstorm, along with damage to sidewalks and traffic signals.

    Public Works Committee
  7. Staff estimated that 30 to 50 sidewalk panels may need replacement at about $400 each, for an estimated total above $20,000.

    Public Works Committee
  8. Staff said storm work will likely reduce this year’s colored-concrete crosswalk work from two locations to one and delay planned City Hall parking-deck repair or replacement.

    Public Works Committee
  9. Staff identified pressure on the Solid Waste Utility budget and said leaf collection may be shortened by two to three weeks to help offset storm-related costs.

    Public Works Committee
  10. The Library Board received a city representative’s update that included storm damage among current city matters; the board took no action on the topic.

    Library Board