Two Rivers’ utilities committee received a nearly $4 million low bid for lead-service-line work, while staff reported wastewater compliance problems tied to industrial discharge and treatment-plant bacteria.
No public comments or communications recorded for this meeting.
Staff reported that part of the sanitary sewer work was complete and about half of the water-main installation had been finished. The next work included storm sewer at the 12th Street intersection, with public works staff planning to pave driving lanes there to keep vehicle traffic moving.
Staff said the annual CMAR scores were comparable to the prior year, but the utility again failed influent measures and also failed BOD measures. Staff said the influent problem was likely connected to Riverside Foods discharge and expected improvements there within months; February BOD problems were tied to filamentous bacteria. Staff planned to meet with the Department of Natural Resources on May 16 and expected a new permit soon afterward.
The electric utility received its new digger truck April 22 and put it into service after on-site training April 24. The truck cost $318,000. Staff said the 1992 truck would be auctioned later in the summer after Roosevelt Avenue utility work is complete.
Staff reported that Columbus substation Unit #1 was repaired with new wiring replacing old butt-spliced, corroded wiring. The unit now has the same configuration as Unit #2.
Staff reported Unit #2’s control-wire upgrade was repaired April 17 after the unit had been out of service since July 2023. Separately, the city attorney presented Frontier with a replacement for its 1967 pole-rental agreement, including a requirement to move underground when city electric lines do. Frontier had not responded for three weeks, and staff were seeking a list of poles affected by its contractor’s drilling.
Staff said the utility would review its 2002 contract with Charter. On Roosevelt Avenue, crews were continuing utility work that includes replacing about 12 poles and transferring power to the new poles.
Staff reported Dalton Schmidt was promoted from within to Water Distribution Foreman and certified water operator, serving as the outside-work lead. He will remain part of the plant’s five-week rotation.
Staff said punch-list work was completed the prior week and the south water tower was inspected. The inspection checked roof-to-wall connection issues, with documentation expected soon.
Staff said the water utility must complete a records-based, citywide inventory of service-line materials this year; unknown materials may remain in the inventory. After the inventory is complete, the utility has 30 days to notify owners of lead or galvanized service lines. Staff also said the utility must maintain a map available for review on request, though it does not have to be publicly posted.
Staff reported the Rack 5 membrane replacement had been postponed three times since the start of the year. The utility had hoped to complete the installation before summer in case of high water flows.
Staff said Two Rivers uses the Woodland Compost Site for leaf collection and resident use. Manitowoc County wants an agreement with Two Rivers similar to its agreement with the City of Manitowoc; staff said it would add costs that must be budgeted and would bring the agreement back for committee review.
Staff reported approval for an extension of leachate collection at the north landfill. The matter was expected to return to the committee for review.
Staff reported Mammoth Construction was the low bidder for the 2024 lead-service-line contract at $3,969,410. The funding memo assumed 300 water-service lateral replacements, including 200 private-side replacements, but staff said existing funding was short by about 71 services. Staff estimated a private water-lateral cost of $2,956 less a $2,500 contribution, leaving $456 for the owner to pay or place in a loan program; estimated sanitary-lateral cost was about $3,431.