Two Rivers’ utility committee flagged a funding problem for lead-service-line replacements and a grease blockage that distorted wastewater readings after heavy June rain. No public comments or substantive votes were recorded.
No public comments or communications recorded for this meeting.
Staff reported that the sanitary sewer main was complete. Crews were finishing the water main, water services and sanitary laterals, with water-main completion expected the week of July 8 before work shifted to the main storm sewer.
The lead service line replacement contract had been awarded and was awaiting a preconstruction meeting. Manitowoc County said its ARPA contribution could be used only for public-side water-service work and would match city ARPA spending only on those same items. That left the city without a settled funding path for the $2,500 grant it had provided to help owners with private-side replacements; staff was exploring whether tax funds could repay part of a state loan on an owner’s behalf.
Riverside Foods told city staff it did not expect construction to begin until fall because its contractor was booked, though it was checking whether work could start in mid-August. Staff linked recent wastewater-plant problems to significant fat, oil and grease buildup and said the state environmental agency was seeking an on-site meeting and inspection of Riverside’s processes.
The first phase of Sandy Bay Highlands 3 was out for bids, covering part of Orchard Lane, its cul-de-sac and Rawley Court, with an optional extension of Orchard Lane and Sandy Ridge Drive. Staff expected to send an award recommendation to City Council on July 15. Construction was not expected to begin until after the Sept. 12-14 Manitowoc County Parade of Homes.
Staff said heavy rain June 19-21 produced much higher apparent incoming wastewater flows than outgoing flows, but no untreated wastewater was released and the plant retained capacity. An inspection found a partially blocked pipe caused by solidified fat, oil and grease, creating a backwater condition and misleading flow readings. The blockage was cleared, but staff continued monitoring pH after grease reached a primary clarifier.
Five field employees and the electric director responded after the first outage call at 3:39 a.m. June 25, and most customers had power restored by 6 a.m. A downed tree delayed restoration in the Woodland Drive industrial park until about 7:30 a.m.; a later south-side outage beginning around 9 a.m. was restored around 11 a.m. Staff said customer updates were relayed as crews completed work.
Although the agenda listed no water-utility update, the public works director reported that the state had issued a preliminary hearing notice for proposed lead-and-copper drinking-water rule changes. The stated purpose is to align Wisconsin rules with federal lead-and-copper requirements and anticipated federal updates.
Consultant McMahon prepared and updated existing-conditions maps for the stormwater master plan. Staff was reviewing the maps and sending comments back, with modeling data hoped for by the end of 2024.
Wet conditions delayed repairs to the landfill’s northerly seep to avoid further damage to vegetation and the landfill cap. Staff said early-May investigation did not require more sampling of other possible discharges. It also reported increased flow into the collection system, believed to be groundwater from outside the landfill rather than water passing through the clay cap.
Greg Buckley reported that the June utility newsletter was mailed separately from utility bills because it included the annual water-quality letter required to be sent to property owners and users by the end of June. Staff reported no update on the Frontier Communications project.