Two Rivers’ utility committee reported major gaps in stormwater pollution reductions for two watersheds, while staff said updated modeling and added practices could close them. The committee also tracked lead-service notices, overdue utility bills and upcoming street work.
No public comments or communications recorded for this meeting.
Staff said the Wisconsin Department of Natural Resources indicated its funding is likely in place and that bids came in favorably. The city was preparing assessment rates, rolls and notices for an April 21 public information meeting and hearing at the City Council meeting, followed by a planned award of the low responsive bid to Vinton Construction.
Staff reported that the east-side scattered lead service lateral project was out for bid. No award or other committee action was recorded.
Staff said Riverside Foods’ latest test results were much lower than those discussed the prior month because the company was not producing on that line. Elevated suspended solids and biochemical oxygen demand were still recorded, and another meeting was scheduled for April 17.
Staff reported 914 past-due utility accounts totaling about $433,000. Customers needed to bring accounts current or make payment arrangements by April 15.
Columbus Substation Unit No. 1 had been out of service because of equipment failure. EPS completed repairs, and the unit returned to service March 21.
The utility had about 300 A4 electric meters in stock and had ordered 1,000 more. Staff said A3 meters are no longer made.
Electric installation for Sandy Bay Phase 3 was scheduled for mid-April after property lines were marked. Staff expected the work to be completed in early May.
The city canceled its prior maintenance contract and hired a new contractor to inspect concerns about the quality of the east water tower paint job. Staff said the roof did not appear to have major structural problems, but inspection results were still needed before recommendations could be made; the south tower interior will need future painting.
The Department of Natural Resources approved revisions to the city’s service-line inventory. The city sent notices to an additional 1,600 property owners where records show the public-side line is not lead but the private-side plumbing could not be verified.
Staff reported that existing practices meet required reductions in the West Twin River watershed, with modeled reductions of 42.3% for sediment and 30.5% for phosphorus. But current modeled reductions fall short in the Forget Me Not Creek and East Twin River watersheds, where the city must meet separate sediment and phosphorus targets. Staff said revised modeling, the new high-efficiency street sweeper and additional practices should allow compliance, and the consultant is expected to present at a future joint meeting of the Environmental Advisory Board and Public Utilities Committee.
The landfill contractor had mobilized, but the city first needed testing to create a waste profile for garbage planned for shipment to Ridgeview Landfill. Staff said that process was completed April 7 and the city was asking when the contractor could begin installing the required collection system.
Staff submitted the annual recycling report to the Department of Natural Resources. They reported no notable issues and said the city expects to receive the full recycling payment allocated during the fall 2024 application process.