Two Rivers utilities staff flagged a widening gap between the city’s written street-assessment policy and its actual practice, while water-loss and recycling concerns also remained unresolved.
No public comments or communications recorded for this meeting.
Contracts awarded the previous month were still being executed. Staff said preliminary discussions with Vinton Construction had occurred and the start was pushed to about mid- to late July because of the bidding and award timing. Staff said the revised schedule should still allow the required work to be completed.
The contractor was still working through lead-service-lateral replacements and concrete patches from work completed last year and earlier in 2025. As of April 30, staff reported 98 public-side water services, 104 public-side sanitary laterals, 28 private-side water services and 11 private-side sanitary laterals remaining in the scattered replacement work.
The 2025 lead-service-lateral project had been bid and was expected to go to City Council for an award later that evening. Staff said the city would need executed contracts submitted to the Wisconsin DNR to receive state funding for the project.
The sewer-lining project had been bid and was expected to go to City Council for an award later that evening. Staff said executed contracts would then be sent to the Wisconsin DNR so the city could receive state funding.
New wastewater pumps and bases had been delivered. Installation was planned for later that week and was expected to take two days.
A new wastewater flow meter was installed but was not producing appropriate measurements. The vendor replaced communication cable, then determined the sensors were also defective; replacement sensors were ordered.
Staff submitted a working copy of the wastewater Capacity, Management, Operation and Maintenance plan to the Wisconsin DNR. The agency said it wants two certified collection-system operators—one from wastewater and one from public works—because maintenance duties are split between those groups. Staff said no further discussion had occurred on how to meet that requirement while controlling costs.
Annual transformer testing at Columbus Substation Unit No. 2 was scheduled for May 22, with the unit expected back in service by May 30. Staff said customers should not experience service interruptions.
The Electric Utility planned its annual electronics recycling day for June 10 at the utility buildings off Lake Street.
The Frontier pole-attachment agreement was complete in concept but still awaited signatures from all parties. Staff thanked Boardman and Clark for legal work supporting the Electric Utility.
Ten private wells within the city needed renewed permits. The permits operate on a five-year cycle, and renewals were due this year.
The Water Utility used satellite leak detection for the first time and found 20 leaks, including three considered significant. Staff reported approximately 16% water loss in 2024, while the Public Service Commission’s ideal is below 15%. The report identifies a system-efficiency problem but records no repair plan or committee action.
Water Utility staff planned annual emergency-response refresher training. Staff said the training is intended to ensure employees know what to do if an emergency occurs and the utility director is unavailable to help make decisions.
Staff said turbid Lake Michigan water had lasted longer than usual this spring. The utility said it could manage the condition, but it required additional maintenance at the front end of the treatment process.
Staff said the shoreline-improvement project kickoff meeting included a tour from the wastewater plant to the southerly wayside to identify erosion-control opportunities and places where hard surfaces could be replaced with native vegetation. A joint meeting of the Environmental Advisory Board, Advisory Recreation Board, Plan Commission and interested council members was planned for July 23 to review 30% alternatives, including a possible expanded beach near the wastewater plant and native plantings on city land.
Most landfill work was complete, including installation and backfilling of drain tile. Wet conditions delayed completion of the clay cap, final site restoration and replacement of a lift-station pump. Staff reported substantial groundwater flow through the new collection pipe.
A resident complaint to the Wisconsin DNR about recycling handling and bins led the agency to contact Public Works. Staff said Manitowoc County advised that the city is not required to provide bins or covered bins. The city said automated collection with larger carts would bring substantial costs, including new carts and trucks, and could raise charges to residents.
Staff told the committee that the written assessment policy calls for adjacent property owners to pay 75% of eligible project costs, with the city paying 25%. But after a 2019 committee discussion, the city has generally charged adjacent owners about 30% and absorbed nearly 70%. Staff said the purpose was to alert the committee to the mismatch and that the city would examine how to proceed over the coming months.