Two Rivers’ utilities committee backed a county compost-site agreement starting in 2025 while staff reported new wastewater monitoring requirements, a delayed water-tower renovation and pending insurance claims.
No public comments or communications recorded for this meeting.
Sanitary sewer and water-main work, private sewer laterals and water services were completed within the project area. The contractor was working on storm sewers and expected to move to road grading, gravel and paving after that work. The city said voters would have access across Roosevelt Avenue at Hawthorne Street on Aug. 13 for the Abundant Life Church polling place, with signs directing them there.
A new wastewater discharge permit took effect Aug. 1, 2024, and runs through July 31, 2029; the previous discharge limits stayed in place. The permit replaces summer fecal-coliform testing with twice-weekly, year-round E. coli monitoring and adds PFAS, nitrogen, nitrite, nitrate, chloride and arsenic monitoring. Staff must also submit a revised sewer-maintenance program by Oct. 31, 2024, a sludge-management plan by year-end, and reports on PFAS results in 2025 and 2026.
Staff shared a contractor schedule for Riverside Foods work beginning Sept. 4. The work was expected to include cutting and removing pavement, excavation, tank and piping installation, concrete work, asphalt patching and final striping by Sept. 20.
Repairs to substation unit No. 2 were completed. The utility reported an $80,400 insurance payout after the $5,000 deductible was subtracted from an $85,400 proof of loss.
The utility is renegotiating a Frontier Communications pole-attachment agreement that dates to 1967 and covers the Columbus Street-to-State Highway 310 area. After reviewing Frontier’s proposed revisions with Boardman & Clark, staff sent a revised proposal back to Frontier.
The utility completed electric service to Braun Truss and installed new or relocated transformers at L.B. Clarke. Paragon received new service, but the utility was running both services while the customer sorted out an electrician’s error involving which panels each service supplied.
MSA was mapping water-service materials in a geographic information system for the utility’s lead-service compliance work. Staff said the results would not be published online but could be accessed at the utility office. The utility will need to notify properties with lead, galvanized-replacement-required or unknown service lines.
The utility began its second round of lead-and-copper testing using the same list of properties as the prior round. Staff reported that 20 of 60 samples had been completed.
The new rack 5 membranes had been operating for two to three weeks. One membrane failed but was replaced under warranty.
The south water tower’s mixing pump will be replaced by another vendor. Staff said the utility uses mixing pumps to keep water fresh in its tanks; the east tower pump was replaced in 2023 after both tower pumps failed in 2022.
A consultant reviewed the south tower, and staff said its paint remained in acceptable condition. The tower will not be painted in 2024; staff said painting may be needed in roughly two to three years.
A switchgear failure is expected to cost between $80,000 and $100,000 to replace. Staff planned repairs for February or March, intended to seek insurance coverage and expected to include repair costs in the 2025 budget. A temporary process using electric-utility personnel was in place.
Engineering staff reviewed and commented on existing-condition maps needed to establish a baseline for future stormwater modeling. The maps were returned to the consultant in late July.
The committee supported a proposed agreement beginning Jan. 1, 2025, for Two Rivers to use Manitowoc County’s Woodland Drive composting facility after the county closes that site in the fall. The draft proposed a 12½-year term and a $9,000 annual payment; staff planned to request billing after Jan. 1 so the cost could be budgeted. Staff said the city could not operate a local yard-waste and compost facility for that annual amount.
The committee received a property owner’s request to compost human waste. Staff said the city had no specific ordinance or regulation on the issue and that state law allows it subject to federal disposal requirements.